Hello Everyone,
Just a topic on Change Order but Internal. Say a situation like,
"Its a Engineering Project. The Client has given the Scope of Work and the Contractor has prepared a deliverable list. But at one time Contractor came to know that this deliverables are not enough as per the scope of work. So we need to prepare more deliverables. So internally the Project Manager asks the perticular dicipline engineer to prepare those extra deliverable which was not accounted in the Original Deliverable List." This Change cannot be issued as a change order to Client as it was already in the original scope.
So how would you manage such a Change. Has someone managed such a Internal Change.
Regards
Jithin