Hi I hope this has been posted in the right place...
I have a situation where a contractor has had a clause 31 programme accepted however from day one the construction team are undertaking works in a different sequence... they clause 32 is due in 3 weeks time however we are trying to monitor the current programme with our construction programme and using collaborative planning session.
Changes are also taking place which under the NEC have to be assesed using the accepted programme for delay, In this situation would I be in the right to request an updated programme before the clause 32 is due citing that works are not being carried out as planned??
Updating the programme has become difficult due to this choping and changing as we don't know what order they will undertake the works...