HI
Can anyone provide a list of tips when saving a .pp file as an .xer file and importing to P6. I always get error message in Asta, and when i import to P6, it crashes and forces me to Exit with an error code.
I found an independent list (see below) but wanted to see if anyone knew of more? Our contractor is currently working in Asta and will be migrating to P6 but I need to run a quick analysis of the integrity of the schedule as it stands and want to be sure I'm importing everything I need.
Thanks