The contract contains multiple unit completion penalty milestones which are waived if the final completion milestone is achieved. The project is in serious delay. The contractor has submitted an EOT claim (TIA and owner delay events only) that is focused on delay to final completion milestone and ignores all the intermediate penalty milestones. In my opinion all penalty milestones should be included in the analysis - any comments please.