Hello Eveyone,
Just a doubt and the situation is a little bit different. "Mike" Probably you might know if its a valid point to ask for Claim. The situation is (Example)..
In the original Scope from Client - 4 Wells will be drilled and given. You have to do the Pipeline work from the 4 wells to the Tank where the Oil would be Stored and the completion date as per the Contract for this work is 30th April 17.
Actual Scenario - The Client was not able to drill the 4 well but was able to complete on 3 well. So the Client is asking to do the Pipeileline from the 3 wells to the Tank for now.
The Question,
From the above scenario is the Completion date of the Contract of 30th April still valid or we can ask for an Extension of Time.
When I look at it, I feel that it is Valid as 3 or 4 well you can still send the Oil to the Tank. So the scope has reduced. So isnt the 30th April date as per the Contract still valid.
Regards
Jithin