I have updated my data date and updated the remaining durations for activities but a few would have a remaining duration of 2 days, but the forecast finish date would be two week out.
The predecessor was complete (both start and finish checked complete). Also, the gnatt char bar separates the actual progress from the remainng duration.
Has anyone seen this problem and know the solution?
Thank you for your help.