I have a situation where I have a task of 25 days duration that cannot be split and a shutdown period of one month. What I'd like to be able to setup within Project 2013 is the 25 day task so that it ends no later than the start of the shutdown period or starts no earlier than the end of shutdown period.
I have assigned a resource that does not work during the shutdown period but what happens is that the task starts before shutdown and ends after shutdown (so a 4 week delay in the middle).
Is there anyway to make the task completely jump to after the shutdown period?
Obviously I can put a dependency in but that defeats the purpose, I'd like Project to do the scheduling completely.
Paul