All,
I have a resource loaded schedule, where in Level of Effort activities the Remaining late units are pushed behind the DD and Remaining Early Units are pushed after the Finish Date. There is no negative float and no contraint on the schedule, I have also checked that the Calendar's are consistent.
Thanks for all help,
Pranab