In higlighted line why my budgets units calculating from unit % completion as i selected Physical % completion and in project settings also i changed to Physical.
Kindly reply how to update i want my budgte popints calculated from physical % completion i tried all methods but no use.
i want actual budget units comes 50% as physical instead of 27% of Units %