Hi All,
Presently Im working on EOT Claim analysis to be submitted to my client.The problem Im facing now is that I dont have any progress schedules in primavera despite of a recovery schedule prepared by a former planner.Also I have planned to do AsBuilt versus Planned analysis,so should I update the schedule on baseline schedule itself.Should I keep the data date same as that of baseline start date because the project has been delayed by 2 years but this delay has happened with client knowledge itself.So my doubt is what should be the data date to schedule my As built schedule and is my method the appropriate means to do thos analysis.