Hello Everyone,
I have 2 criterias for an activity
1. It can be done only in Day time (0600 to 1800)
2. Activity cannot be left undone even if its 90% finished.
e.g. Activity duration is 4 Hrs. and its starting on 1500 - then it should automatically moved onto next day.
While doing baseline i managed to make it happen wih help of Constraints & change in logic.
However, my worry is while in operation if this situation arises then P6 will just schedule it with current logic. that means activity will be split between 2 Days (1500 to 1800 3Hrs + 0600 to 0700 1hrs next day).
Is there any way to get this things right throughout?