Hello,
I am currently managing a portfolio of plans that are managed by entering progress and actuals. The duration type is set to Fixed Duration & Units and % complete type is physical. All resources have been set to Auto Compute Actuals and Calculate costs from units in the resource settings.
I want to identify remaining labor units by entering progress. P6 is calculating the remaining labor units by deducting the actual hours booked to the activity instead of deducting the earned hours from the budget.
I know this can be done as I have worked in a system before with the same settings.
Can anyone advise if there is a setting that needs to be selected to calculate the remaining hours based on progress %?
Thanks,