Dear All,Below are our situation on the contract schedule.
Contract Schedule | 1-8-2014 to 1-8-2016 |
BL Programme | Approved by Client on 30-8-2014 |
Updated Schedule was submitted by Contractor | as of Aug14,Sep14,Oct14,Nov14,Dec,14. |
Recovery Programme | Client have asked Contractor to submit recovery programme, recovery programme was prepared and approved by Client in Jan2015. This is used and updated to date. |
Variation Order - V.O.(increase of internal plaster thickness) - Issued in Dec2014 and Approved by Client in Mar2015. Now my question is, in doing time impact analysis, which programme should I use? If the VO approved date was Mar.2015, then I could use the Mar.2015 update of the programme which was the recovery programme.Thanks in advance!