Hi all! We have an approved schedule that the block works and internal plaster activities are combined (single activity only with 30 days duration). Client issued variation order to change internal plaster thickness, now my problem is how can you link the delay event to internal plaster activity if block works and internal plaster are single activity only? Thanks in advance!