In a design and built contract, the contractor submitted a eot claim due to delay in a permit. A revised completion date was awarded to the contractor.
Since it is a design & built contractor the real quanties and clear scope was not defined in the beginning. But with the contractor's experience he submitted the baseline and got approved.
Now the contractor wants to add few more activities in the eot approved baseline, but he will finish all activities within the revised completion date.
Can the contractor add those activities or the client can approve it?
Best Regards
Kannan