Hello,
I'm schedulling an engineering job, MEP.
the plan for mechanical as follows:
there are 3 desginers, each will take a division - pluming 1 engineer, HVAC 1 engineer, and FF 1 engineer.
each have a drawing list with assigned hours for each drawing, and WBS is agreed.
FF desginer will be the first to finish, so, I want him to support pluming, but only after he finishes his given task.
then when both FF and pluming finish, I want them to support HVAC.
How can I do that on P6.
Thanks in advance.