Hi all,
As I keep on thinking about P6 remaining early start description, I keep getting confused. The description says ' Remaining early start is basically the earliest date an activity in-progress can start or continue after the data date'.
My question is why would an activity in-progress start or continue? As it is already progressing why describe it as continuing?
Is this just a poor description? I will appreciate if somebody can throw more light on this.
Thank you.
Anthony