Hi,
I am new to Microsoft Project, but has much experience with Safran Project. Is it possible to get MS Project automatically set free float of a activity as the activity's duration?
Ex. on follow-on activities.
I also miss the "planned progress" coloumn, but according to google that is impossible without using formulas which hardly works. Or is it a solution without using formulas?
Thank you in advance.
Regards