Dear All,
What will be the effect of updating an out of sequnce activity in a Baseline programme (Cost loaded) in a Villa Project.
Planned dates of that activity falls in the month of May, but actvity completed in the schedule period. (Schedule % is 0, Activity % is 100).
How will it affect the Performance % ?. Settings for EV calculations are as follows.
1. Performance % equal to Activity %
2. ETC is equal to remaining cost.
3. Budgeted values with current dates.
4. Progress override
Best Regards,
Sunil.