It is generally noted and as per this: http://www.ronwinterconsulting.com/rabaseline.htm [1] point #92 that having having a Lag in a FS is not a good practice. Can someone pls provide more insight into my situation as below (Construction Project):
The predecessor is finishing on 10/02/15 while the successor will have to start on 10/04/15. I have a FS with 59d lag but a colleague (who is a planning consultant) advises that a lag should NEVER exist in FS relationship. Please assist in shedding more lights.
Thanks.
Ade.