Quick question - is it possible to write a macro to edit "Project options" in Project 2010? Specifically I'm looking to write 2 macros to change the date format to Date+time and back to Date only.
Useful if you quickly want to see exactly why an activity is taking 7,74 days for example and "clean up" unnecessary decimals.
(As an aside - who the ยค#& knows what it means to spend 0,74 days doing something anyway? I wish Project would let you round off to whole days and let you see the exact decimal by selecting the cell, just like in Excel. Maybe in a future version?)
/Andrei