Dear all, I am preparing my Recovery Schedule now & one of my consultant asked me to prepare a mean curve i.e. 60% from Early Unit & 40% Late Units. In this regard my Data Date of the Schedule is 12-Sep-2014 & when i am looking @ my Remaining Late Unit its shows units distributed in the month of July & August 2014, furthermore my completion of the project is 30-June-2015 even though the units are showing in the month of July 2015 as well. I have checked that non of the activity having negative float & i have applied the constraint on my Milestones but the units are still showing beyond the limit. any help in this regard will be highly appreciated. thanks wysiwyg_imageupload:: [1]