Dear All;
I have an approved baseline & now client is asking to add scope of work that was not initially include in the contract.
we have EOT of 30 days to accomodate these extra activities.
Can I change (delay) existing activities by 30 days also.
or
I have only right to show new scope in 30 days of EOT and keep existing schedule the same?
I also need some clause or reference to validate.
Thanks