1990 – 2004 Modern Continental Companies– Planning and Scheduling Manager in charge of assisting the project management team in developing a feasible and reasonable work plan for all phases of each construction contract. Assigned highly trained schedulers to each contract to implement work plan and monitor progress utilizing the project schedule as the primary tool. Provided project support on an ongoing basis, assisting in preparing schedule related correspondence and communication with all parties involved with the project. Other responsibilities include: senior level oversight and negotiations for all time entitlements on all capital construction contracts.
Capital Projects:
Central Artery Tunnel, Boston, MA
Owner: Massachusetts Transit Authority
Contracts: C01A2, C07A1, C07A5, C09B1, C09B2, C09B3, C09C1, C09C2, C09C4, C17A1, C17A2, C17A6, C17A9, C19E1, C19E6, C19E7
Contract value: over 2.5 billion total <?xml:namespace prefix = st1 />CAT contracts
DeerIslandWaste Treatment Facility
Owner: Massachusetts Water Resources Authority
Contracts: CP260 Secondary Treatment Facility Clarifier “C”
CP043 Late Site Prep and Demolition CP160 Ancillary Design Modifications
Contract value: 200 million total
Route 3 Design/Build Project
Owner: Massachusetts Highway Department
Contract value: 385 million
AlamedaCorridor Rail Improvements
Owner: Alameda Transportation Authority
Contracts: Dominguez Channel Bridge, South End Seg. 3, Long Beach Leads, Del Amo Bridge
Contract value: approx. 50 million total
PasadenaBlue Line Design/Build
Owner: LA to Pasadena Metro Blue Line Authority
Contracts: Chinatown Aerial Structure Design/Build
Contract value: 21 million
Other Projects:
Corporate Scheduling Manager in charge of all scheduling oversight and functions:
Massachusetts
Terminal E – Massport
West Garage - Massport
Russia Wharf & Fort Point Channel Tunnel – MBTA
BrightmanStreet Bridge– MHD
IndependenceWharf- MCC
Various utility projects – City of Cambridge
California
WestBasin Intermodal Facility – Port of LA
Pacific Coast HwyMicrotunnel – City of Santa Monica
Walnut CreekMicrotunnel – EBMUD
San FranciscoBay BridgeRetrofit - CalTrans
San Luis ObispoCuesta Grade Widening – CalTrans
LaCanadaBridgeRetrofit – CalTrans
MissionValley East LRT – San Diego MTDB
Virginia
GriffithWater Treatment Plant – Fairfax County Water Authority
Pentagon Microtunnel – DOD
Florida
Nova Road SR-5, Port Orange - FDOT
Nova Road SR-5, Ormond Beach – FDOT
West Palm BeachViaducts – FDOT
New York
Long IslandExpressway I, II & III – NYDOT
WantaghBridge- NYDOT
Rhode Island
ProvidenceCSO Microtunnel - NBCC
WashingtonBridgeI-195 - RIDOT
Other projects with Modern Continental:
South Boston Haul Road, SouthBoston, MA– CAT - 1991Project Scheduler
Eastern Ave Bridge, Fall River, MA – MHD - 1991Project Manager
Casey Overpass, Roslindale, MA – MDC - 1990Construction Superintendent
SPC Concrete, Atlanta, GA 1988-1990
Hillside Office Bldg., Waltham, MA - 1989
Project Engineer
Westin Hotel, Waltham, MA - 1988
Field Engineer
Bartons’ Crossing Apartment Complex, Alexandra, VA - 1988
Field Engineer
Other Construction Related Experience:
Various construction companies 1976-1988
Construction Survey Party Chief
Construction Superintendent