Hello,
There is a problem when i update the schedule and mark the activity as started my activity finish date automatically moves ahead. Example For an activity A my start date is 12.Oct.2013 and finish date is 15.oct.2013. When i update the schedule and move my data date to 13.Oct.2013 my finish date automatically moves to 16.Oct.2013