I've been asked to review a Contractor's P6 Schedule - Only a hard copy is available at this time.
There are several activties that are 100% complete with the Actual Start & Finish dates noted, none of the dates have constraints. Since the activity has been completed with an actaul finish date, shouldn't the Late Finish be the same as the actual finish?
Harold