Sheth Creators Pvt. Ltd. – Mumbai
PROJECT CONTROLS MANAGAER November 2012 – Present
Duties:
· Receive, review, negotiate and finalize the fee proposals of Architects (Design & Landscape) & various consultants (Lighting, Façade, Interior Designing, Car parking, Security etc) after preparation of comparison sheets and consulting from the Director.
· Determine design changes and schedule slippages impact.
· Develop and maintain establish standards to exhibit schedule and plan hierarchy and inform project and company management.
· Understand, practice and lead organization’s commitment by example to achieve zero incident safety.
· Coordinate with cross functional team with professionalism, courtesy and tact.
· Determine significant irregularities, trends and variances and suggest corrective action.
· Coordinate with project management staff to ensure project objectives and timelines.
· Gather inputs and update standard management reports.
· Create, review and manage project schedules to identify progress, lead times and project sequences.
ANC Contracting India Pvt. Ltd – Gujarat (GIFT City)
PROJECT CONTROLS MANAGER March 2012 - November 2012
· Develop and maintain schedules and collect status updates for tasks.
· Working with the project team to develop a project plan, including facilitating processes for handling risks, issues, scope, quality and general project communication.
· Track scope changes and gather data and analyze impact of change.
· Analyze variations, slipping tasks, impact of task changes, critical path, and overall ability of project to deliver on time.
· Preparing a project status reporting on a set interval basis i.e. provide a project dashboard giving a high level view of the project’s health
· As part of schedule development, determine that the project has all needed resources. Ensuring resource allocations are current i.e. that a resource has adequate project hours to cover tasks and has the availability to work on project.
Sheth Developers Pvt. Ltd - Mumbai
MANAGER COORDINATION July 2009 - February 2012
· Receive, review, negotiate and finalize the fee proposals of Architects (Design & Landscape) & various consultants (Lighting, Façade, Interior Designing, Car parking, Security etc) after preparation of comparison sheets and consulting from the Director.
· Developing Baseline programs using MS Projects at the Pre Contract stage.
· Conducting periodic site visits to check the progress, quality and safety compliance and reporting critical issues to the Director.
· Coordinating with relevant departments in the organization to ensure progress at site is not hampered.
· Making daily, weekly and monthly report for director’s review.
Reliance Retails Pvt. Ltd- Mumbai
MANAGER May 2008 - March 2009
Gammon & Billimoria LLC-Dubai, UAE
PLANNING ENGINEER January 2006 - April 2008
· Development & maintenance of project master construction schedule/revisions/catch-up plans in coordination with project team.
· Resource Loading, Scheduling, Progress monitoring, updating, controlling and reporting periodically.
· Preparation of cash flow forecasts
· Preparation of Pictorial charts and other graphical representation of Project.
· Preparation of planning procedures and progress measurement systems
· Attending the progress meetings and reviewing the progress for the week.
· Conceptualize the detailed project reports; take off Documents, Primavera Project execution program and execution plans after thorough discussion with Clients, selection of Sites.
· Assist in maintaining, improving and continually updating planning systems, procedures, processes and standards
· Extension of Time, Claim Analysis.
Other Responsibilities handled while working for the company:
· Wealth Care Investments- B+G+13+2 storey Pent House Residential show rooms building: Preparation & approval of project master construction schedule, detailed resource loading and producing of various progress, manpower & cash flow curves.
Jumeirah Lake Towers– Parking Garage Works: Updating of project master construction schedule, resource loading and producing of various progress, manpower & cash flow curves