Dear colleagues,
I imported a project plan into MS Project 2007 from Primavera P6. For the first 12 activities, the start and finish dates were the same. But starting from the 13th activity onward, I've noticed that the start and finish dates in projet plan generated in MS Project were not the same anymore from the source in Primavera P6. That is why the Project Finish Date and the Total Project Duration were also not the same. Kindly help me out how could I make sure that when I import a porject plan from P6 into MS Project would give the same data/info.
Best regards,
Leonard T. Esber