· Responsible for preparing all documents relating progress measurement and monitoring.
· Analyze drawings, specifications and SOW for preparation of activity networks for project planning and scheduling.
· Preparation and implementation of three month and four week look ahead plan
· Updating four week look ahead plan on a regular basis for project management reporting.
· Coordinate with Resource Coordinator for manpower & equipment requirements and overall coordination to ensure optimum utilization of resources.
· Prepare status reports and maintains the issue register and lesson learnt register.
· Preparation of baseline program master schedule base on project requirements and perform critical path analysis
· Leveling of required resources (man & machines) based on geographical requirements of project to complete the job within planned duration and budget;
· Prepare & implement progress monitoring system
· Progress variance analysis (Baseline, current and mitigation).
· Maintains liaison with the project and field personnel for schedule revisions and updates
· To monitor the progress of work against the baseline schedule and preparation of weekly and monthly management reports.
· Updating baseline program master schedule base on regular basis in order to know the health of project for management review and further action.
· Develop Action and Recovery plans to support project delivery on time.
· To monitor and assign work to Site Engineers in accordance with Company’s policies and procedures and limits of authority.
· To handle procurement activities relating to contracts and sub contracts in accordance with Company’s Procedures and Procurement department activities.