START Date:
May, 2011
END Date:
November, 2011 • Main Unit planner and scheduler for Crude, Vacuum and Hydrocracker Process Units, site preparation and common areas. (purchasing and subcontracts) Engineering, Procurement and Construction, Overall responsibilities for those units,
• Monthly report for client and weekly internal. Project is 3.4 billion US$ and 29000000 Man-hours. using Primavera P6, engineering, procurement (level 5 E and P and level 3 for C). Development level 4 construction. Support to the preparation and issuing of monthly reports to project management. Weekly and monthly meeting. Weekly and Monthly reporting