Hi everyone,
I'm using P3 and have a 4500 activities schedule. The problem I'm facing is the following:
The total float of the last activitiy of the project is -10 days, and I have within the program activities with -15 days of total float. I thought that the total float of the project should be at least the same as the lower total float of the activities (so the last activity of the project should show -15 days of total float).
I really don't understand how is this happening and how to solve it, i would appreciate some help.
¡Thanks!