Dear all,
I just downloaded the trial version of Asta Easyplan and was playing around with it. So far neither in menus nor in help file could I find a resource leveling option. Can somebody help me to pint out to the right place?
I am looking for what is MS Project is done by Tools=>Level Resources and in Spider is called Resource Constrained Scheduling