If I have an activity, and the calendar for that activity is on a 7 day work week calendar but there is a resource assigned to that activity that has a resource calendar that is 5 day work week, will that limit my activity to 5 days a week?
So if activity "A" used an excavator who's resource calendar is 5 days a week, does P3 assume you can only work on activty A 5 days a week?
Thanks in advance.