CROWN STEEL FABRICATORS INC.
428 F. Manalo St.,
San Juan, Metro Manila
Duties :
· Supervised daily construction activities and ensures that plans and specifications are observed.
· Primarily involved in supervision, implementation of fabrication and erection of structural I-Beams/Channels.
· Involved in quantity estimates for the materials requirements at site.
· Prepared program of works and schedule using PRIMAVERA 2.0 and monthly progress billing.
· Prepared materials requisitions and Coordinates with sub-contractors and supplier’s needs.
Position : Site Engineer
July 2001 – January 2003
Project : Construction of 3-Storey Commercial Building
Araneta Avenue, Quezon City
Owner : Mrs Lily Chua
Project Description: Commercial establishment good for textile warehouse and restaurant. Consist of 2,300-sqm-floor area.
Project Cost : Php 12,500,000.00
November 2000 – July 2001
Project : Construction of 5-Storey Residential & Commercial Building
Doroteo Jose corner Rizal Avenue, Manila
Owner : Mr. Joseph Tay
Project Description: Consist of 200 sqm per level in total of 1,200 sqm in floor area. Ground floor will be a supermarket while 2nd and 3rd floor will be restaurant and department store. Remaining two floors is for studio type units.
Project Cost : Php 18,000,000.00