Hi,
I'm trying to find a way of getting a 5 day task to start on the first working day of a week, regardless of the day it's predecessor finishes. For example, Task A finishes on a Thursday, then I want task B to start on the Monday, not the Friday.
I know I could put a lag in the link, but this only works until I update the schedule and task A may move.
I have also considered setting up a calandar that shows Monday only as a work day, then adding in a milestone with this calendar, which in turn drives task B which would do the job. However, it would be neater if i could add a "Must start on a Monday" type constraint, and was wondering if anyone has done this previously.
Many thanks.