I am working on an As-Built schedule using daily reports showing total manpower in each day for Demolition.
the job is coded such that every floor has its own code (I can't add floor codes). But the demo crew worked on multiple floors, so I need to create a different activity for each floor. How would I assign the manpower across the demolition activites for the day?
Any help would be appreciated.
thanks
Jon Grove