Mar 2009 to date Current Job Title : Scheduling Manager Employer : SEPCOIII(Shandong Electric Power Company III) City & Country : Damman, KSA Project : TRANSCO Grid station construction
|
RAS Al KHAIRPOWER AND DESALINATION PLANT-PHASE 1
Near Dammam, Kingdom of Saudi Arabia,
Open Cycle and Combine cycle 3041MW
Contractor:ASC .JV (ACC and SEPCOIII).
EPC Contractor with all Engineering, Procurements, Construction and Testing & Commissioning of Plant till its Handing Over
My Job Responsibilities here includes:
- EPC Milestone Schedule Preparing and Monitoring
- EPC L1,L2,L3 schedule preparing, resource loading and monitoring
- Schedule preparing for the subcontractor, major equipment delivery
- Loading the Contract Price Activity wise in the Schedule.
- Preparation and Generation of Progress Curves of the EPC Project and Devising the Method of progress Measurement as per Client Requirement.
- Productivity Analysis Report Preparation per System to see the Efficiency of the Project Area and Zone wise.
- Critical Path analysis for the overall EPC Project. Marking the Long leading Activities and suggesting the Corrective actions.
- Analysis of Subcontractor’s/vendor’s weekly and Monthly Reports. Giving our subcontractors/vendorstargets for construction on weekly and Monthly basis.
- Supervising Equipment deployment and Material Procurement Plan development by Planning Engineers.
- Preparation of Monthly Presentation/reportfor Client.
- Progress update for Monthly invoice and also identification of Extra works other then Contractual Scope.
- Preparation of Monthly Progress for the Client.
- Preparation and maintaining the Budget in coordination with Cost Control Officers.
- Progress Verification for Engineering, Procurement & Construction with Client.
- Answering Contractual letters written by Client, Our Consortium partner ACCand Sub-Contractors.
- Conducting meeting with Our Site Construction Teams, Sub Contractors & Client to increase the productivityand resolve the issues.
- Preparing the Top Most critical items for the Project & Reporting them to the company top management.
May 2008to Oct 2009 Job Title : Sr. Planning Engineer Employer : SEPCOIII (Shandong Electric Power Company III) Country : Jordan |
EPC contract for a combine cycle of the 2 gas turbines
1*108MW
Scope of work contains site works for Civil works, Mechanical works, Electrical works, I&C works etc
My Job Responsibilities here includes:
- Preparation and approval of Level 4 baseline & Latest Forecast Plan (on Primavera Project planner).
- Preparation of man power mobilization plan for direct & in direct employees.
- Preparation of equipment mobilization plan.
- Preparation of material requirement plan.
- Preparation of internal budget for the project.
- Preparation of weekly and monthly progress Report for Client. The reports contains Updated Level 4 plan on Primavera, Actual Progress Report as per site conditions.
- Productivity and efficiency calculations on FWBS (Field work Break down structure) Basis.
- Progress S curves preparing
- Monthly report to the client preparing
- Coordination meeting with subcontractors
- Critical path analysis for the whole project
- Monitoring the engineering and material delivery schedule match with the site works
March2007to October2008 Job Title : PlanningEngineer Employer : SEPCOIII(Shandong Electric Power Company III) Country : India
Project : TRANSCO Grid station construction
|
Malula project coal power plant 1*108MW EPC contract
SEPCOIII
Scope of work contains site works for Civil works, Mechanical works, Electrical works, I&C works etc
My Job Responsibilities here includes:
- Preparing and monitoring the milestone schedule for the whole site works
- Preparing the L4 schedule for site works together with each discipline
- Preparation of daily, weekly and monthly reports for the client.
- Weekly meeting, monthly meeting preparing for internal and subcontractors
- Critical path analysis for the whole project
- Monitoring the engineering and material delivery schedule match with the site works
- Preparation of impact analysis report on weekly basis for any variation in the original scope of work.
Qinzhou Guangxi Coal PowerPlant
August2005to March2007Job Title : Civil engineer/Planning Engineer Employer : SEPCOIII(Shandong Electric Power Company III) Country : China
Project : TRANSCO Grid station construction
|
2*600MW Unit
South of China Guangxi Province
My Job Responsibilities here includes:
- Civil works for the site work.
- Help in the preparation of Invoices.
- Preparation of material Requirement plan.
Mar 2005 to July2005 Job Title : Trainee civil engineer Employer : Jian An civil construction company Country : China
Project : TRANSCO Grid station construction
|
My Job Responsibilities here includes:
- Technical works support for the civil site works.
- Lining and some basic works.
- Monitoring site manpower.