Hi All
A topic im sure has been discussed many times before but as new judgments are provided in court and the industry evoles maybe opinions/outlooks change.
In terms of constructive accleration such as performing overtime without an official request from the client to mitigate delays [both excuseable and not] , what are your thoughts in relation to cliaming for these costs?
Assume lump sum contract model and a Shut-down milestone in contract. The Shut down having an influence on the scenario as a Company would have to plan their shutdowns 'down to a tee' and advise suppliers and customers etc.
Yes we have a similar problem and are going ahead with the claim as we must, but curious to see what the difference of opinions are on this topic.
Thanks in advnace.
Regards
Aidan