Greetings of the day,
Ownership of float, whether it belongs to employer or contractor. Is it necessary to mention in the contract, if it is not mentioned in the contract to whom it will belong.
For example an employer delayed a non critical activity for 90 days and the float for that activity was 50 days. bcoz of this the project got delayed. Is contractor eligible for an EOT 90 days or just only 40 days.
Thanks n Best Regards