START Date:
January, 2003
END Date:
November, 2004 Major Duties:
- Prepare Schedules for Drawing submittals, Material submittals (Long lead & Short lead) & develop Concrete/Steel requirement curve from the Contract programme.
- Reviewing & presentation of weekly work progress report, in the weekly progress meeting & material procurement meeting.
- Prepare recovery programs for delays during progress of work.
- Prepare Weekly & Monthly reports for Clients & Head office.
- Worked as a claimant by generating database and formats of progress of work. Drafting of Delay/Disruption claims & EOT claims, involved during progress of project. (Emirate Hills infrastructure project)
- Applying Cost Control techniques for resources procuring or hiring.