I am having trouble when I reschedule my programme.
My calendars (both work and resource) are set to 10hr days start 7am - finish 5pm.
When I reschedule my data date to be 26-Nov 00:00 - the activities starting on the 26th show as starting at 7:01 - and not 7:00. This in turn is pushing all my activities starting on 26th out by one date ie. 2 day duration activity starting 26th 7:00 and finishing 28th 17:00. But instead it is showing the activity as starting 26th 7:01 and finishing 29th 7:01.
I have checked my settings time and time again and nothing seems to be working.
Need help asap please if anyone is out there reading this.
Thanks : )