START Date:
April, 2011 - Reviewed and commented on contractor’s monthly interim payment for IK construction, IK Materials and OOK Material.
- Provided schedule input for MPU (Monthly Progress Update) & BISR (Budget Item Summary Report) for building works, civil works, electrical works, instrument works, insulation works, mechanical works, painting works, pre-commissioning works, special lining works and telecommunication work.
- Prepared and updated Construction Progress Tracking and generated additional reports for Senior Project Engineers and Project Manager’s information and usage.
- Coordinated issues related to Project Monitoring and Interim payment with the contractor’s Project Control Manger, Cost Engineer and Planning Engineer.
- Prepared and tracked project cost and schedule performance analysis, maintain visibility of milestones to all members,
- Reviewed the contractor construction schedule, progress S-curve, manpower histograms, pre-commissioning and look-Ahead schedule.
- Modified original contractor schedule and provided additional tracking schedule using Primavera (P3 or P6) for Saudi Aramco Engineers per area of responsibility like common area, gas/oil separation (GOSP Train 1), gas /oil separation (GOSP Train 2), gas /oil separation (GOSP Train 3), TEG & Gas Treatment unit, ATM & HP Gas Compression unit, Oil inlet Facilities (East Manifold Area), KO Drum & Main Pipe Rack Area, Flare Area, Main Pipe Rack (GOSP area), North GOSP area for Satellite office and CSW ponds.
- Prepared additional reports as required by PMT’s and Senior Project Engineer.
PROJECT
Manifa Core Hydrocarbon Facilities & Cogeneration (Contract No. 6600020534 IK Value: 2,621,320,984.65 usd & Contact 660020533 OOK Value: 1,478,227,150.71 USD)
Contractor: Snamprogetti KSA.;