Hiya folks, I'd just like to ask that after reading the following scenario, and assumingq that both the Client and the Contractor have agreed that the valuation wil be done by a QS. I'd just like to know how the QS would value it. (I'd appreciate it if you can add figures to explain)
Scenario:
In contract week 3, whilst constructing the ground floor slab, the contractor has encountered a ‘soft spot’ which necessitated a redesign of the foundations and the introduction of piling to the south east corner of the building. This has caused a delay of 3 weeks.
Regards,
Faz