I have leveled my resources however they remain over allocated in some instances. That said, I would like to know if it is possible to view the "resource usage profile", select a "time period" to display the respective activities for that resource(s), then go into the "activity details" to adjust allocated resources if applicable; however when I do this, the "activity filter" for the "time period" from the "reource usage profile" is lost when I click the "activity details" tab. I was therefore looking for a way to keep that "time period" filter from the "resource usage profile" while I am in the "activity details" tab. Any help on this would be much appreciated. Thank you for your time and have a good day.