Hi All,
I have searched for this answer but cannot find,
At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)
What box do I tick to instead show "% complete" on the Y-axis (based on budgeted units, not actual values)
I have tried changing "Time Units" to "Show as Percentage" in the User Preferences, no change.
Many thanks
Sam D