Dears,
I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it
Sorry for my bad language
Regards