I have set two tasks in automatic mode: one task after another using predecessors link as defined below. Task A is completed in 100%.
Id | |Task Name | |Predecessors | |Start | |Finish |
265 | |Task A | |264 | |Fri 24/06/11 | |Mon 27/06/11 |
266 | |Task B | |265 | |Fri 29/07/11 | |Thu 04/08/11 |
What I don't understand is why MS Project schedules Task B a month after the first one. I'm particularly missing feedback from MS Project justifying this decision. Without this feedback nailing down the problem and its reason becomes hard.
- What could be the possible reason for that?
- How can I get feedback from MS Project with explanation why the given task has been scheduled in a certain way?
Some more details here:
- Task B contrain type is "Start as soon as possible"
- Resources assigned to the task have no holidays in this period (no exceptions in calendar)
Thank you in advance,
Maciej