Hi Gentlemen,
I needed opinion of professional planners.
The situation is that i am getting a couple of activities that are placed in my schedule so that it is not possible to assign them any successor.As a result the end is open end.Is it Right to assign them a finish milestone as a phase finish milestone and continue with the schedule????????????
Regards
Engr.Faiz