Was wondering if anyone could help me on this one.
I am currently exporting a plan from P6 using the PM XER version 5 option (have also tried using contractor version 5), when the plan is then imported into our clients system (they are using P3E) the budgeted units are lost or increased randomly across some activities throwing out all the programme calculations. Some of the activities have remained the same so I am not sure what is happening with this. It also happens when I export and re-import the file into my P6.
If anyone has any idea's I would really appreciate some help with this one.
Cheers
Donna