Dear Experts,
Is there any work around to show in the ghantt chart bars the actual bar completion inside the baseline bar.
for example in the when i view the baseline bar if the perticular activity is scheduled to finish 50% complete then in the baseline bar half of the bar should be one color and the other half another color.
can this be done in p6.
Thanks in advance